1-51 St Peters Close (odd numbers)

  • Should the walkways between the blocks be secured to create separate areas that can be secured by boundary fences and gates linked to a door entry system?
  • Does the block need new windows?
  • What is the condition of the roof? Does it need to be replaced by a pitched roof?
  • Does the block need cavity wall insulation?
  • How can the parking areas on the Estate be secured?

Property Tenanted/Leaseholder Breakdown

Block

Properties

Tenanted

Leasehold

Year built

St Peters Close (1-51 odd)

26

10

16

1976

LBTH Estimate for Required Expenditure, 2001

Category Description

Group Name

Total over 30 years

Catch Up Repairs

Boundaries

1,717

Catch Up Repairs

Decorations

4,409

Catch Up Repairs

Electrics

3,376

Catch Up Repairs

Floor coverings

446

Catch Up Repairs

Floors

228

Catch Up Repairs

Heating/hw

1,948

Catch Up Repairs

Internal doors

1,175

Catch Up Repairs

Kitchens

1,889

Catch Up Repairs

Plasterwork

542

Catch Up Repairs

Structure

113,997

Catch Up Repairs

Walls

114

Future Major Repairs

Ancilliary buildings

1,048

Future Major Repairs

Boundaries

3,926

Future Major Repairs

Decorations

22,045

Future Major Repairs

Electrics

20,722

Future Major Repairs

External doors

1,566

Future Major Repairs

Floor coverings

2,026

Future Major Repairs

Heating/hw

16,533

Future Major Repairs

Internal doors

7,535

Future Major Repairs

Kitchens

28,336

Future Major Repairs

Lighting

6,297

Future Major Repairs

Roof

7,956

Future Major Repairs

Sanitary ware

18,249

Future Major Repairs

Stairs/Balconies/Security

5,152

Future Major Repairs

Structure

5,267

Future Major Repairs

Windows

39,076

Block Improvements

Stairs/Balconies/Security

19,260

Dwelling Improvements

Electrics

668

Dwelling Improvements

Kitchens

1,145

TOTAL

336,649

 

 

Proposed Essential Works from Offer Document 4th Draft

North Side of Old Bethnal Green Road

The following tables identify by block the refurbishment works proposed in the first 4 years if the transfer goes ahead.

St Peters 1-51 (odd)

 

Essential works to bring all properties up to a good standard

 

Structural Works

 

Concrete and brickwork repairs

y

External decorations and works to entrance screens

y

Cavity wall insulation

y

Flat roof repair / renewal

y

Parapet repairs

y

Asphalt and balcony repairs

y

Internal Refurbishment

 

New kitchen, bathroom and WC

y

New or overhauled heating system

y

New double glazed windows

y

Overhaul existing windows

 

Replace / overhaul front entrance door

y

Rewiring or repair existing electrical installations

y

Internal repairs and asbestos removal

y

Services

 

Drainage repairs

y

Overhaul / replace rainwater goods as necessary

y

Repairs and decoration to communal areas

y

Full replacement of electric laterals and risers

 

Overhaul water tanks

y

Bin chamber refurbishment

y

Lightning protection

y

Replace block lights as necessary

y

Overhaul door entry system

 

CCTV installation

(subject to consultation)

y

Lifts

 

Overhaul of existing lift

 

Works to areas around blocks

 

Fencing repairs and decorations

y

Semi-defensible space to ground floor flats

 

Improve hard landscaping and signage

y

 

 

 
 