2-20, 22-42, 44-54 Mansford Street, & 58,59 Nelson Gardens
- Should the walkways between the blocks be secured to create separate areas that can be secured by boundary fences and gates linked to a door entry system?
- Does the block need new windows?
- What is the condition of the roof? Does it need to be replaced by a pitched roof?
- Does the block need cavity wall insulation?
- How can the parking areas on the Estate be secured?
|
Mansford Street (2-54 even) | 27 | 7 | 20 | 1976 |
Category Description | Group Name | Total over 30 years |
|
|
| Catch Up Repairs | Ancilliary buildings | 1,074 | Catch Up Repairs | Boundaries | 1,374 | Catch Up Repairs | Decorations | 7,041 | Catch Up Repairs | Electrics | 687 | Catch Up Repairs | Floor coverings | 298 | Catch Up Repairs | Heating/hw | 1,030 | Catch Up Repairs | Internal doors | 2,349 | Catch Up Repairs | Kitchens | 3,778 | Catch Up Repairs | Lighting | 287 | Catch Up Repairs | Plasterwork | 724 | Catch Up Repairs | Rainwater goods | 1,266 | Catch Up Repairs | Roof | 19,784 | Catch Up Repairs | Sanitary ware | 1,431 | Catch Up Repairs | Stairs/Balconies/Security | 411 | Catch Up Repairs | Structure | 171,125 | Catch Up Repairs | Walls | 1,773 | Catch Up Repairs | Windows | 41,699 | Future Major Repairs | Ancilliary buildings | 7,200 | Future Major Repairs | Boundaries | 5,151 | Future Major Repairs | Decorations | 35,205 | Future Major Repairs | Electrics | 28,303 | Future Major Repairs | External doors | 8,005 | Future Major Repairs | Floor coverings | 1,117 | Future Major Repairs | Heating/hw | 18,344 | Future Major Repairs | Internal doors | 6,369 | Future Major Repairs | Kitchens | 27,592 | Future Major Repairs | Lighting | 11,162 | Future Major Repairs | Rainwater goods | 4,811 | Future Major Repairs | Roof | 53,377 | Future Major Repairs | Sanitary ware | 18,613 | Future Major Repairs | Windows | 11,748 | Block Improvements | Stairs/Balconies/Security | 28,890 | Dwelling Improvements | Electrics | 7,610 | Dwelling Improvements | Kitchens | 916 | Dwelling Improvements | Walls | 2,748 | | TOTAL | 533,291 |
North Side of Old Bethnal Green Road
The following tables identify by block the refurbishment works proposed in the first 4 years if the transfer goes ahead. | Mansford Street 2-54 (even)
| Essential works to bring all properties up to a good standard | | Structural Works | | Concrete and brickwork repairs | y | External decorations and works to entrance screens | y | Cavity wall insulation | y | Flat roof repair / renewal | y | Parapet repairs | y | Asphalt and balcony repairs | y | Internal Refurbishment | | New kitchen, bathroom and WC | y | New or overhauled heating system | y | New double glazed windows | y | Overhaul existing windows | | Replace / overhaul front entrance door | y | Rewiring or repair existing electrical installations | y | Internal repairs and asbestos removal | y | Services | | Drainage repairs | y | Overhaul / replace rainwater goods as necessary | y | Repairs and decoration to communal areas | y | Full replacement of electric laterals and risers | | Overhaul water tanks | y | Bin chamber refurbishment | y | Lightning protection | y | Replace block lights as necessary | y | Overhaul door entry system | | CCTV installation
(subject to consultation) | y | Lifts | | Overhaul of existing lift | | Works to areas around blocks | | Fencing repairs and decorations | y | Semi-defensible space to ground floor flats | | Improve hard landscaping and signage | y |
|
|
|